Bushfire Assessment Reports NSW DA 2026: Planning for Bush Fire Protection, Section 4.14 and When an RFS Bush Fire Safety Authority Is Required

26 October 2026 by
Bushfire Assessment Reports NSW DA 2026: Planning for Bush Fire Protection, Section 4.14 and When an RFS Bush Fire Safety Authority Is Required

Answer first: If your NSW site is mapped bush fire prone, your DA will generally need a bush fire assessment report showing compliance with Planning for Bush Fire Protection 2019. Under section 4.14, council must be satisfied of compliance or hold a recognised consultant's certificate. Residential subdivisions and special fire protection purposes also need an RFS Bush Fire Safety Authority.

By: giantA Pty Ltd · Updated 27 October 2026

Bush fire can change a building's materials, siting, driveway, water supply and landscaping all at once. On Hills, Northern Beaches, Sutherland and Blue Mountains fringe sites we often see the drawings nearly finished before anyone checks the map. This guide covers when councils need a bush fire assessment report, which pathway applies, what changed when the Development Coordination Authority (DCA) started on 1 July 2026, and how to sequence the report.

What is a bush fire assessment report and when does council need one?

A bush fire assessment report assesses the site's bush fire hazard and shows how the proposal meets Planning for Bush Fire Protection (PBP), published by the NSW Rural Fire Service (RFS). The prescribed version is PBP 2019. Planning Circular PS 21-010 (revised 1 July 2026) states that DAs on bush fire prone land are generally required to include a bush fire assessment report.

The trigger is mapping. Bush fire prone land is land recorded on a council's certified bush fire prone land map under section 10.3(2) of the Environmental Planning and Assessment Act 1979 (EP&A Act). RFS guidance explains that the map shows Vegetation Categories 1, 2 and 3, plus a buffer of 100 metres around Category 1 vegetation and 30 metres around Categories 2 and 3. A lot can be mapped with no bushland on it.

Check the mapping through:

  • the NSW Planning Portal spatial viewer;
  • the RFS online bush fire prone land check tool; and
  • your section 10.7 planning certificate, which notes whether the land is bush fire prone.

Maps are recertified at least every five years and can be amended at any time, so check the current map. PS 21-010 also notes councils can seek RFS advice under section 4.15 even where land is not mapped.

Which pathway applies: section 4.14 or a Bush Fire Safety Authority?

Section 4.14 of the EP&A Act covers most development on bush fire prone land, including dwellings, alterations and additions, dual occupancies and multi-dwelling housing. Council cannot grant consent unless it is satisfied that the development conforms to the prescribed version of PBP, or it has a certificate from a person the RFS recognises as a qualified consultant in bush fire risk assessment stating that the development conforms.

Section 100B of the Rural Fires Act 1997 requires a Bush Fire Safety Authority (BFSA) for two types of development: a subdivision of bush fire prone land that could lawfully be used for residential or rural residential purposes, and development of bush fire prone land for a special fire protection purpose (SFPP). The SFPP list includes schools, child care facilities, hospitals, hotels, motels and other tourist accommodation, seniors housing, group homes and retirement villages, plus purposes added by regulation. A DA that needs a BFSA is integrated development under section 4.46 of the EP&A Act.

Proposal typeMain provisionWho assesses bush fireWhat you typically lodge
New dwelling, knock-down rebuild, alterations and additions (infill)EP&A Act s4.14; PBP Chapter 7Council, with DCA consultation only where compliance is not establishedBush fire assessment report or RFS Single Dwelling Application Kit (if council accepts it); calculated BAL on plans
Dual occupancy, secondary dwelling, multi-dwelling housingEP&A Act s4.14; PBP Chapter 8Council, with DCA consultation where neededBush fire assessment report by a qualified consultant
Residential or rural residential subdivisionRural Fires Act s100B; integrated developmentDCA issues general terms of approval; RFS issues the BFSA after consentFull report addressing PBP Appendix 2 (A2.1) and Chapter 5
SFPP (school, child care, seniors housing, tourist accommodation and similar)Rural Fires Act s100B; integrated developmentDCA, then RFS for the BFSAFull report addressing A2.1 and Chapter 6, often with a Bush Fire Management Plan
Complying developmentCodes SEPP and related SEPPsCertifier; the RFS has no roleBAL certificate showing the site is not BAL-40 or BAL-FZ
State significant developmentExcluded from s4.14 by s4.14(1B)State SSD assessmentNo BFSA required (RF Act exclusion)

Development that needs a BFSA cannot be complying development, and the BFSA requirement does not apply to internal alterations. If your pathway is unclear, start with our guides to exempt development vs CDC vs DA and CDC vs DA.

What changed on 1 July 2026 with the Development Coordination Authority?

From 1 July 2026, councils send bush fire referrals to the DCA instead of the RFS.

Consultation for section 4.14 development. The new section 4.11 of State Environmental Planning Policy (Planning Systems) 2021 (commenced 1 July 2026) requires council to give the DCA written notice of a DA on bush fire prone land no later than 14 days after receiving it, and to take into account DCA comments received no later than 28 days after the notice. Importantly, the section does not apply where council is satisfied the development complies with PBP, or where it has been given a qualified consultant's certificate confirming compliance. Subdivision and SFPP development follow the BFSA route instead.

In practice, a solid report and consultant certificate can keep a compliant dwelling DA out of the State referral queue.

Integrated development and the BFSA. RFS guidance on issuing a BFSA for integrated development from 1 July 2026 states that the DCA now determines the general terms of approval (GTAs) during the DA, and the RFS no longer issues GTAs for those applications. After consent is granted, the applicant applies separately to the RFS for the BFSA before carrying out the development. Under section 4.50 of the EP&A Act, the RFS must grant the BFSA where consent followed the GTAs, the application is made within three years of consent, the consent has not lapsed or been revoked, and the application is consistent with the approved development.

The BFSA application must include the clause 45 information under the Rural Fires Regulation 2022, the consent, the DCA-issued GTAs and the approved plans and reports. DPHI guidance says DCA gives a single consolidated response within 28 calendar days. For background on the DCA itself, see our DCA explainer.

What must a bush fire assessment report contain?

PBP Appendix 2 sets the submission requirements. The level of detail depends on the pathway.

ItemInfill development (PBP A2.2)BFSA development (PBP A2.1, RF Reg cl 45)
Statement that the site is bush fire prone landRequiredRequired, with property description and address
VegetationLocation, extent and formation of bushland on or within 140 m of the siteClassification to PBP out to 140 m from the property boundaries
SlopeSlope and aspect of the site and of bush fire prone land within 100 mSlope on and around the property out to 100 m
Environment and heritageLikely environmental impact of proposed protection measuresSignificant environmental features, known threatened species or communities, known Aboriginal objects or places
Protection measuresSite plan showing access, water, APZs, BAL and footprint; mitigating featuresSetbacks and APZs, water supply, road capacity, two-way access, emergency access and egress, maintenance plans and emergency procedures, construction standards, sprinklers and other measures
BALCalculated BAL construction levelsConstruction standards for building elements
Compliance statementCompliance with PBP Chapter 7How the proposal conforms with, or departs from, PBP Chapters 5 to 8, plus any registered certified fire trails

For subdivisions, A2.1.1 notes a conceptual plan with building envelopes may be requested (a 15 m by 15 m envelope is assumed unless specified), and staged subdivisions must show APZs, access and water at every stage.

How is the BAL calculated in NSW?

The Bushfire Attack Level (BAL) measures how severely a building could be exposed to ember attack, radiant heat and direct flame contact. PBP section 7.7 explains that NSW modelling uses the inputs and the Detailed Method (Method 2) of AS 3959, and that the BAL tables in PBP Appendix 1 replace the AS 3959 tables in NSW. The six levels are BAL-LOW, BAL-12.5, BAL-19, BAL-29, BAL-40 and BAL-FZ (flame zone).

The inputs are vegetation formation, effective slope and distance to the hazard, which is why an accurate detail and level survey matters. For what each BAL means for construction, read our BAL ratings guide.

What do the PBP protection measures mean for your design?

For residential infill, PBP section 7.4 groups the protection measures as APZs, access, water supply, electricity and gas services, construction standards, landscaping and emergency evacuation. Each must be met by an acceptable solution or a justified performance-based solution.

MeasureWhat the report testsTypical design consequence
Asset protection zone (APZ)Separation between the building and the hazard, managed to a fuel standardBuilding position on the lot; conflicts with tree retention and biodiversity
AccessFirefighting access and safe egressDriveway width, turning areas, passing bays on longer driveways
Water supplyWater available for firefightingHydrant access or a dedicated static water supply
ConstructionConstruction matched to the calculated BALGlazing, cladding, decking, screens, gutters and subfloor details
LandscapingPlanting and fuel management close to the buildingSpecies, spacing and garden beds near walls
Emergency managementEvacuation and emergency planning, especially for SFPPBush Fire Emergency Management and Evacuation Plan

The infill objectives in PBP section 7.3 include providing defendable space around the building, achieving better bush fire outcomes than currently exist on the site in proportion to the scale of works, and not putting a greater bush fire management responsibility on neighbouring landowners. Section 7.8 adds that where alterations are proposed to a dwelling built before 2002 with few protection measures, consideration must be given to upgrading the existing building. PBP also says fences within 6 m of a building, or at BAL-29 or higher, should be non-combustible.

APZs often clash with other reports. Coordinate the bush fire consultant with the arborist report, any biodiversity assessment and the landscape plan. Vegetation clearing rules can also apply, as covered in our tree removal and clearing guide.

Who can prepare a bush fire assessment report?

Section 4.14 lets council rely on a certificate from a person recognised by the RFS as a qualified consultant in bush fire risk assessment. The RFS fact sheet on suitably qualified consultants explains that recognition works through an RFS-accepted accreditation scheme with peer review, insurance, conduct standards, continuing professional development and auditing. Practitioners must also meet competency requirements through an RFS-approved tertiary qualification or an approved assessment of comparable experience.

For smaller infill proposals, PBP A2.2 notes that the assessment can be done relatively simply with the RFS Single Dwelling Application Kit and a site diagram. The RFS cautions that not all councils accept the kit, so check before relying on it. For more complex applications or any performance-based solution, PBP recommends engaging a recognised consultant to prepare the report and a Bush Fire Management Plan.

What is the step-by-step process for a bush fire DA?

  1. Confirm the mapping. Check before concept design.
  2. Identify the pathway. Section 4.14, BFSA (subdivision or SFPP) or complying development.
  3. Commission the survey. Pick up slope, levels and vegetation towards the hazard.
  4. Engage the bush fire consultant early. Get preliminary BAL and APZ advice at concept stage.
  5. Design to the constraints. Site the building, driveway, water and landscaping to achieve a workable BAL and APZ within the lot.
  6. Coordinate other reports. Align arborist, biodiversity, landscape and stormwater documents with the APZ and access.
  7. Finalise the report and certificate. BAL, APZ dimensions and plan references must match the final drawings.
  8. Lodge and respond. Lodge through the Planning Portal and answer any DCA or council requests consistently.
  9. After consent. For integrated development, apply to the RFS for the BFSA before starting work. Carry bush fire conditions into the construction certificate.

Our DA checklist and DA/CDC checklist tool show where the report sits among other lodgement documents. For complex sites, a pre-DA meeting with council helps.

Is Planning for Bush Fire Protection changing?

PBP 2019 remains the version prescribed by section 271 of the Environmental Planning and Assessment Regulation 2021. It was legislated on 1 March 2020, and RFS guidance notes that DAs lodged before that date are assessed against PBP 2006. Two addenda apply:

  • the 2022 Addendum aligns PBP with NCC 2022 for Class 9 SFPP buildings; and
  • the January 2025 Addendum deals with primary and secondary schools, including access and internal tenability.

The RFS exhibited a Draft Planning for Bush Fire Protection 2026 from 6 August to 3 September 2026. A draft cannot be relied on for assessment until the final document is published and recognised in legislation.

Why do bush fire reports trigger RFIs?

The most common causes are avoidable:

  • the report refers to an older plan revision, so footprints, setbacks or BAL notes no longer match;
  • the APZ relies on land the applicant does not control, or on neighbours managing their vegetation;
  • slope was estimated rather than measured, or measured in the wrong direction;
  • the landscape plan puts dense planting inside the APZ;
  • the access, turning area or water supply in the report does not appear on the architectural plans; and
  • the Statement of Environmental Effects describes the bush fire position differently from the report.

Frequently asked questions

Do I need a bush fire report if only part of my lot is mapped?

Generally yes. Section 4.14 applies to development on land recorded as bush fire prone, and the mapped buffer often covers only part of a lot. The resulting BAL may be low, but council still needs the assessment.

Is a BAL certificate the same as a bush fire assessment report?

No. A BAL certificate states the bushfire attack level and is the key document for complying development. A bush fire assessment report is broader and addresses APZs, access, water and landscaping as well as the BAL.

Can I use a CDC on bush fire prone land?

Sometimes. Complying development is not permitted on land at BAL-40 or BAL-FZ, and a BAL certificate is needed before the CDC is issued. Development that needs a Bush Fire Safety Authority cannot be complying development.

Does the RFS still review my DA after 1 July 2026?

Not directly in most cases. Councils now refer bush fire matters to the DCA, which issues GTAs for integrated development. The RFS still issues the Bush Fire Safety Authority after consent for subdivisions and special fire protection purposes.

How long is a BFSA application window after consent?

For integrated development, section 4.50 of the EP&A Act and RFS guidance say the RFS must grant the BFSA where the application is made within three years after consent was granted, the consent has not lapsed or been revoked, and the application is consistent with the approved development.

Can the draft PBP 2026 be used for my DA now?

No. The draft was exhibited from 6 August to 3 September 2026, but PBP 2019 remains the prescribed version until a new document is finalised and recognised in legislation.

How giantA can help

giantA prepares DA documentation for sites across Greater Sydney and NSW, including bush fire prone lots where siting, BAL construction and APZs need to be resolved early. We coordinate the consultants so the report and drawings match at lodgement. Explore our services and architectural services, or ask us about your site. For the wider process, see our NSW DA process guide.