By: giantA Pty Ltd · Updated 22 November 2026
Answer first: Archicentre Australia's 2026 Cost Guide puts new construction, including extensions to an existing building, at $2,700 to $5,100 per m² including GST. That is a basic shell and extended roofline only. A kitchen, bathroom or laundry is added on top, and so are service upgrades, repairs to the existing house, landscaping and professional fees.
This guide is for Sydney homeowners planning a rear extension. It uses the published Archicentre figures for the build, shows how to add them up for a simple example, explains what the rate leaves out, and sets out how CDC and DA timing, BASIX and design fees fit around the construction cost. We have not added any construction figures of our own: where the guide has no rate, we say so.
Rear extension cost in Sydney: what the 2026 guide says
The figures below come from the Archicentre Australia Cost Guide (CostGuide 2026, PDF). Archicentre describes them as indicative, general advice that assumes standard materials, fixtures and finishes, good site access and a relatively simple roof. The guide states that its cost advice includes GST.
| Item / scope | Indicative cost (incl. GST) | Source and notes |
|---|---|---|
| Rear extension shell (single storey): basic shell and extended roofline | $2,700 to $5,100 per m² | Archicentre 2026, "New constructions, including extensions to an existing building" |
| Double-storey / first floor addition | No separate rate in the guide | Listed as "allow extra for" (stair, structural work to the existing building, roof alteration). Needs a project-specific price |
| Kitchen (wet area fit-out) | $23,000 to $49,000 | Archicentre 2026, added to the shell rate; white goods extra |
| Bathroom / ensuite (wet area fit-out) | $17,500 to $35,000 | Archicentre 2026, added to the shell rate |
| Laundry (wet area fit-out) | $10,000 to $19,000 | Archicentre 2026, added to the shell rate |
| Structural work (steel beams, footings, roof tie-in, demolition) | Not itemised in the guide | The guide lists "structural work to existing building" and "adverse ground conditions" as extras for additions but gives no rates. Your engineer and builder price these |
| Service upgrades (electrical, plumbing, heating), repairs to the existing house, paving and landscaping | Excluded from the shell rate | Archicentre 2026, additions note 4 |
| Design and drawings | Quoted per project | Request a giantA quote; see the fees section below |
| BASIX, council or certifier fees, consultant reports | Quoted per project / set by the council or certifier | Depends on the site and pathway; see the fees section below |
A simple worked example (our arithmetic, not a quote)
To show how the pieces add up, assume a 30 m² single-storey rear extension with a new kitchen and bathroom. The 30 m² is only an example size. The ranges below are the Archicentre rates above, multiplied or added, and they are still indicative and include GST.
| Step | Calculation | Running total (incl. GST) |
|---|---|---|
| Shell, 30 m² | 30 × $2,700 to 30 × $5,100 | $81,000 to $153,000 |
| Add a kitchen | + $23,000 to $49,000 | $104,000 to $202,000 |
| Add a bathroom | + $17,500 to $35,000 | $121,500 to $237,000 |
That total still excludes structural extras, service upgrades, repairs to the existing house, landscaping, design and approval costs, and white goods. The width of the range is the point: it reflects the factors Archicentre lists, such as the extent of documentation, choice of materials, the builder you select, site accessibility, the size of the job and the quality required.
What pushes a rear extension towards the top of the range?
Archicentre's guide names the main drivers, and they are the usual suspects on a Sydney rear extension:
- Site access. The rates assume good access. A narrow side passage or steep rear yard changes how materials and equipment get in.
- Roof configuration. The rates assume a relatively simple roof. A complex tie-in to the existing roof is an extra, not a given.
- Structural work. Opening up the back of an existing house, adding a first floor, or poor ground conditions are all flagged as "allow extra for" items.
- Wet areas. A kitchen, bathroom and laundry need special fittings and fixtures, which is why the guide prices them separately.
- Finishes and builder choice. Standard materials are assumed; custom or premium choices move the figure.
- Size of job. The guide notes larger works can achieve a better value price per square metre.
Archicentre also says a more accurate price comes from a design-specific cost plan, ideally prepared by a quantity surveyor and then tested through competitive tender once the design is developed. Our cost estimating and measured survey services help establish the existing conditions first.
Approvals and design fees: what giantA publishes
Design and approval costs sit outside the construction rate. We only state fees that giantA publishes, all excluding GST and council or certifier fees. Everything else is quoted once we know your scope.
| Item | giantA price (excl. GST) | Notes |
|---|---|---|
| Rear extension design and drawing set (CDC or DA) | Quoted per project | Fixed-fee quote after we confirm scope. Request a quote. See drafting services |
| Amended plans for an existing DA or CDC (section 4.55 / 4.56 modification) | $750 to $2,250 | Published on our drafting page (prices reviewed 20 November 2026) |
| Heritage-sensitive or complex-geometry projects | $4,500 to $10,000+ | Published on our drafting page; only relevant if your house is heritage listed or in a conservation area |
| BASIX certificate | Quoted per project | Required for alterations and additions of $50,000 or more. See BASIX assessment |
| Council DA lodgement fee, certifier fee | Set by your council or certifier | Not giantA fees; confirm with the council or certifier |
| Structural engineer and other consultants | Quoted per project | Depends on the structure and site |
Our renovation and extension service covers concept design, CDC or DA documentation, BASIX coordination and builder-ready documents. The development application and complying development certificate pages explain each pathway in detail.
CDC or DA for a rear extension: which is faster?
Timing affects cost through holding costs, rent and builder availability, so it belongs in your budget. The NSW Planning Portal describes complying development as a fast-track process for straightforward development that meets specific development standards, with approvals issued in as little as 20 days. It is determined by council or an accredited certifier without a full DA.
| Pathway | Timing (NSW sources) | When it applies |
|---|---|---|
| Complying development certificate (CDC) | As little as 20 days (NSW Planning Portal) | The proposal meets every relevant development standard in State Environmental Planning Policy (Exempt and Complying Development Codes) 2008. In metropolitan areas the neighbours within 20 metres must be notified 14 days before approval |
| Development application (DA) | Around 80 days on average (NSW Planning, 14 May 2026) | The design does not fit the complying development standards, or the land is excluded or restricted, for example some heritage conservation area properties |
Two points matter for a rear extension. First, one standard missed means the whole project goes to a DA. The NSW Government has said a proposal failing just one standard currently needs a full DA, and it has exhibited a proposed variations pathway for minor departures; the Planning Portal says it is still reviewing feedback, so do not plan around it until it is finalised. Second, in a heritage conservation area, the Portal says external alterations to a dwelling house under complying development must not be to a wall facing the primary road or increase the height of the dwelling, so many heritage rear additions need a DA. Our guide to CDC vs DA in NSW covers the decision in more depth.
If your house is heritage listed or in a conservation area, read our heritage house extension guide.
BASIX for alterations and additions
BASIX is a NSW requirement for alterations and additions valued at $50,000 or more, whichever approval pathway you use. Because the guide's shell rate alone can reach that value on a modest extension, plan the BASIX inputs (glazing, insulation, hot water, lighting) with the design rather than after it. See the NSW Planning Portal page on BASIX for alterations and additions.
A simple checklist before you set a budget
- Decide the floor area you need and whether it is single or double storey.
- List the wet areas: kitchen, bathroom, laundry, and which are new versus renovated.
- Check the planning controls and whether the land is heritage listed or in a conservation area (section 10.7 planning certificate).
- Ask for a measured survey of the existing house so the structural tie-in is designed, not guessed.
- Allow separate lines for structural extras, service upgrades, repairs to the existing house and landscaping.
- Choose CDC or DA early, because it sets the programme.
- Get a project-specific cost plan before committing to a builder.
Frequently asked questions
How much does a rear extension cost in Sydney in 2026?
Archicentre Australia's 2026 Cost Guide gives $2,700 to $5,100 per m² (including GST) for new construction, including extensions to an existing building. That rate covers a basic shell and extended roofline only. Kitchens, bathrooms and laundries are added on top, and site-specific items are extra, so treat it as a starting band, not a quote.
Is a double-storey rear extension more expensive than a single-storey one?
Usually the total is higher because there is more floor area, but the Archicentre guide does not publish a separate per-m² rate for storeys. It lists first floor additions, including the stair, structural work to the existing building and roof alteration, as items to allow extra for. Ask a quantity surveyor or builder to price your actual design.
Do the per-m² figures include the kitchen and bathroom?
No. The guide says the square metre rates are for a basic shell only and that wet area fit-out must be added. Its 2026 wet area ranges (including GST) are $23,000 to $49,000 for a kitchen, $17,500 to $35,000 for a bathroom or ensuite, and $10,000 to $19,000 for a laundry, with white goods extra.
What costs are not included in the rear extension rate?
The guide says indicative costs do not include upgrading services such as electrical, plumbing or heating, repairs and upgrades to the existing house such as roof and gutter repairs, painting, damp and pest treatment, or paving, landscaping and site drainage. It also says to allow extra for adverse ground conditions, consequential work to the existing building and professional fees.
Does a rear extension need a DA or can it be a CDC, and how long does each take?
It depends on whether the design meets every development standard for complying development under the NSW Codes SEPP. If it does, a complying development certificate (CDC) can be issued in as little as 20 days according to the NSW Planning Portal. If it does not, or the house is a heritage item or in a heritage conservation area, a development application (DA) is usually needed, and the NSW Government has cited an average of around 80 days for a DA.
Do I need a BASIX certificate for a rear extension?
BASIX applies to alterations and additions valued at $50,000 or more, on both the DA and CDC pathways. Given the guide's shell rate, many rear extensions will reach that threshold, so allow for BASIX early in the design.
How much does giantA charge to design and document a rear extension?
giantA quotes extension design and drawing packages per project after confirming scope, because the price depends on the floor area, the approval pathway and the existing house. giantA's published price for amending plans after approval (section 4.55 and 4.56 modifications) is $750 to $2,250 excluding GST. Request a quote to have your extension scoped.
Talk to giantA about your rear extension
giantA designs and documents rear extensions across Sydney, coordinating the measured survey, BASIX and the CDC or DA package so your drawings, approval pathway and budget line up. See our renovation and extension service, read the Sydney home renovation cost guide, or request a quote at giantA.com.au.
This article summarises the Archicentre Australia 2026 Cost Guide and NSW Government planning information as at 22 November 2026. Figures are indicative general information, not a quote or advice for your site. Confirm costs with a quantity surveyor or builder, and approval requirements with your council or certifier.
Sources
- Archicentre Australia – Cost Guide (CostGuide 2026, © 2026 Archicentre Australia; renovations and additions, page 4; PDF)
- NSW Planning Portal – Complying Development (approvals in as little as 20 days; variations proposal under review)
- NSW Planning Portal – What to tell your neighbours (neighbour notification, 20 metre radius, 14 days)
- NSW Planning Portal – Home Renovation (complying development) (updated 29/10/2026)
- NSW Planning – Making it easier to build homes in NSW (14 May 2026: complying development in as little as 20 days versus an average of around 80 days for a DA)
- NSW Planning Portal – BASIX alterations and additions
- State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, via legislation.nsw.gov.au
- giantA published prices: drafting costs and timelines (reviewed 20 November 2026, excl. GST)