Answer first: Most NSW development applications for new buildings or external works need a detail and level survey by a registered land surveyor, with levels to the Australian Height Datum (AHD). Within 1 m of a side or rear boundary, City of Sydney requires it to be based on a boundary survey; Inner West asks every survey to confirm all boundaries.
By: giantA Pty Ltd · Updated 6 October 2026
Does a NSW DA legally need a survey plan?
The Environmental Planning and Assessment Regulation 2021 requires a development application to be in the approved form published on the NSW Planning Portal. The Department’s Application requirements document lists what that approved form contains. It does not use the words “survey plan” for every DA, but it does require a site plan showing the location, boundary dimensions, site area and north point of the land, existing vegetation and trees, existing buildings, existing levels of the land in relation to buildings and roads, and the location and uses of buildings on adjoining sites. Drawings must also show proposed finished levels and proposed methods of draining the land.
In practice you cannot produce those levels and dimensions reliably without a surveyed base, so councils turn the approved form into explicit survey requirements in their lodgement checklists. The Department notes its list is not exhaustive, and the NSW Planning Portal’s applicant guide How to submit a development application to council says to satisfy all of the consent authority’s requirements to minimise delays.
Which survey types matter for a DA or CDC?
“Get a survey” covers several different products, and briefing the wrong one is a common, avoidable mistake. This is the survey work we most often see in Greater Sydney residential packages.
| Survey product | What it shows | When it is typically needed | What it feeds |
|---|---|---|---|
| Detail and level (contour) survey | Structures, spot levels and contours to AHD, kerb, paths, fences, retaining walls, visible services | Almost every DA with external works | Site plan, sections, height, stormwater/OSD, landscape |
| Boundary identification survey | Title boundaries confirmed on the ground, with offsets from buildings, fences and walls | Works within 1 m of a side or rear boundary (City of Sydney); Inner West asks all surveys to confirm boundaries | Setbacks, boundary and party walls |
| Adjoining buildings detail | Neighbouring floor levels, ridge and eave heights, window positions and levels | Where height, privacy or overshadowing is assessed | Shadow diagrams, privacy, SEE, clause 4.6 |
| Tree survey layer | Tree position, trunk diameter, height, canopy and (in some LGAs) base level to AHD | Trees on site and near the boundary on adjoining land | Arborist report, landscape plan, tree protection |
| Title, easements and services | Easements from title, deposited plan and 88B instrument; visible pits and inverts | Sites with easements, sewer or shared access | Stormwater route, footprint, services |
| Subdivision survey | Proposed lots and deposited plan administration sheets | Subdivision (Parramatta requires sheets completed by a registered surveyor) | Subdivision plans, 88B instruments |
Who can prepare a survey plan for a DA in NSW?
Use a registered land surveyor. The Surveying and Spatial Information Act 2002 provides for registering land surveyors so that only appropriately qualified persons carry out land surveys, and constitutes the Board of Surveying and Spatial Information (BOSSI), whose Registrar keeps the register of surveyors. Check registration with BOSSI’s Find a Registered Surveyor search; if a name does not appear, that person is not currently registered.
The technical rules now sit in the Surveying and Spatial Information Regulation 2024, which commenced on 1 March 2025 and replaced the 2017 Regulation. Provisions relevant to DA work include:
- Heights: all heights must be related to AHD or another approved datum, confirmed by closed height difference between two bench marks with accurate values (section 29).
- Boundary surveys: a surveyor defining a boundary must locate each structure and fence within 1 m of the boundary (section 30).
- Identification surveys: a survey that identifies boundaries or locates a parcel in relation to adjoining land must state its purpose and show the relevant boundaries (section 45).
- Reduced-accuracy surveys: a survey not requiring strict accuracy needs a written agreement with the client, and the plan must state the accuracy agreed (section 46).
The City of Sydney’s survey plan specification requires the contour and detail survey to be prepared by a registered surveyor and to show the surveyor’s name and ID number. A designer’s measured sketch or a re-drawn sales plan is not a substitute.
What does AHD mean, and why do councils insist on it?
The Australian Height Datum is the national height reference. The 2024 Regulation prescribes it as the datum surface approximating mean sea level adopted by the National Mapping Council of Australia in May 1971. Levels to AHD are written as reduced levels (RLs).
AHD matters because your DA’s numbers must connect to the numbers that control it. Building height under Standard Instrument–based LEPs is measured from existing ground level, or from AHD where a control is set as an RL. Driveway crossings, kerb discharge, on-site detention and council flood information are all assessed in level terms. A survey on an arbitrary local datum cannot be checked against any of them.
What do Sydney councils say a DA survey must show?
Requirements differ, so read the current checklist for your LGA. Four examples show the pattern.
City of Sydney
The City’s document requirements page and its downloadable survey plan specification require a contour and detail survey with all applications, except a change of use with no external works, an internal fit-out, or signage on an existing structure. Where works are within 1 m of a side or rear boundary, the survey must be based on a boundary survey, with a note confirming this. The plan must show, among other items: true north; a scale generally 1:100 or 1:200; floor levels and ridge heights of existing structures; adjoining structures within 3 m of the boundary, with floor level, ridge height and window levels; spot levels and contours to AHD with benchmark details; trees on the site, street and adjoining land within 3 m; visible services including stormwater pit inverts; top-of-kerb levels; and all easements and rights of way, including party walls. The survey must be accompanied by the deposited plan and a current title less than six months old.
Inner West
Inner West Council’s DA Lodgement Guide for Applicants states that the survey plan must be prepared by a registered surveyor within the last 5 years and give levels to AHD. It must confirm all boundaries, and any boundary redefinition must be done before lodgement. It also asks for ridge heights, setbacks and window and door openings on the subject and adjoining sites; road, footpath, kerb and gutter levels; and, for each tree on site, its spot height at the base to AHD, canopy spread, height and trunk diameter at 1 m. Easements must be shown, and neighbouring window levels for shadow diagrams must come from the submitted survey.
City of Parramatta
Parramatta’s application requirements include a checklist for alterations and additions that asks for a recent site survey plan, prepared and signed by a registered surveyor, with the site plan’s existing levels “as derived from a survey plan”. Council’s stormwater checklist expects stormwater plans to be based on a registered surveyor’s survey to AHD, with spot levels and contours extending into adjoining properties, existing easements, trees and structures, at 1:100.
Blacktown
Blacktown City Council’s small-scale residential DA checklist asks for a survey plan to AHD prepared by a registered surveyor, and says the location and roof ridge and eave levels of dwellings on adjoining properties should also be shown.
How recent does the survey need to be?
There is no single NSW-wide expiry date for a DA survey, so rely on what your council publishes. Of the councils above, Inner West sets an explicit limit of five years. Parramatta asks for a “recent” survey without a number. The City of Sydney sets a less-than-six-months limit for the title that accompanies the survey, and its development application process page lists “an old survey” as the kind of small issue that slows assessment.
Even inside a council’s stated period, update the survey if anything on or next to the site has changed — a new fence, a neighbour’s extension, tree removal or regrading. Objectors notice outdated neighbouring buildings.
How does the survey feed the rest of the DA package?
City of Sydney says it plainly: the contour and detail survey should be the basis for any site plan and design drawings. Inner West asks for the survey, architectural plans and shadow diagrams to be combined in one “full set of plans” file.
- Architectural plans: levels, setbacks and the height plane all start from surveyed RLs.
- Shadow diagrams: neighbouring windows, private open space, fences and ridge lines come from the survey. See our guide to shadow diagrams for NSW DAs.
- Statement of Environmental Effects: compliance tables are only as good as the measurements underneath. See what councils expect in an SEE.
- Clause 4.6 requests: if a building exceeds the LEP height standard, the extent of the breach is calculated from surveyed existing ground level. See clause 4.6 variations in NSW.
- Arborist reports: tree numbering, positions and trunk diameters should match the survey. Inner West requires tree numbers on the landscape plan to coincide with the arborist’s report. See arborist reports for NSW DAs.
- Stormwater and OSD: discharge points, pit inverts, kerb levels and easements are design inputs. See our stormwater and OSD guide.
- BASIX: drawings must show the matters the BASIX certificate requires, so areas entered into BASIX should come from the same surveyed base.
- Dilapidation reports: the survey records what adjoining buildings look like on paper; a dilapidation report records their condition. See dilapidation reports.
Does a complying development certificate (CDC) need a survey?
Often, yes. The Department’s Guide to Complying Development (August 2023) says a survey plan prepared by a registered surveyor is useful and required for some CDCs. It recommends showing adjoining houses, contours, trees, easements and plenty of existing ground levels, to help determine setbacks and building heights. The Planning Portal’s CDC applicant guide notes your certifier may require extra documents.
Complying development is a numbers test: setbacks, height and cut and fill limits are applied strictly, with no merit judgement to cover a missing level. A precise survey matters even more for a CDC than for a DA.
Where do easements and underground services come from?
A detail survey picks up what is visible: pits, hydrants, sewer maintenance holes and kerb outlets. Easements, rights of carriageway and restrictions come from the title, deposited plan and section 88B instrument. City of Sydney asks for current documentary evidence of any easement or right of carriageway the development relies on.
Buried services are a separate step. Before You Dig Australia (BYDA) — the service many still call Dial Before You Dig — gives a single point of contact to request information about underground and overhead infrastructure at a work site, without contacting each utility separately. Coordinate BYDA plans with the survey, and flag any sewer main or drainage line under the footprint before design is fixed.
What RFIs do survey gaps usually trigger?
In our DA and CDC work across Sydney councils, the most common survey-related requests for information are:
- levels not related to AHD, or no benchmark and origin of levels shown
- boundaries not confirmed where walls, eaves or excavation are close to a boundary
- adjoining windows, floor levels or ridge heights missing, so overshadowing and privacy cannot be checked
- trees on neighbouring land, or street trees, not located
- no kerb or footpath levels, so driveway and stormwater design cannot be verified
- easements visible on title but missing from the survey and drawings
- surveyor’s name, registration ID or survey date missing, or a survey older than the council allows
- architectural ground lines and spot levels that do not match the survey
What should you include when you brief a surveyor?
Attach your council’s survey requirements to the instruction, as City of Sydney recommends, and cover:
- Purpose: detail and level survey for a DA or CDC, and whether boundary identification is required
- Datum: levels to AHD, with benchmark and origin shown; contours at a suitable interval
- Extent: whole site, street frontage (City of Sydney asks for the public domain to the road centreline) and adjoining land as your council specifies
- Adjoining buildings: floor, ridge and eave levels, and window positions and levels facing the site
- Trees: on site, in the street and on adjoining land, with trunk diameter, height, canopy spread and, where required, level at the base
- Services: visible pits with invert levels, kerb outlets, hydrants, meters, overhead lines
- Title: deposited plan, current title search and any 88B instrument, with easements plotted
- Deliverables: signed PDF showing surveyor name, registration ID and date, plus CAD (DWG) on the same coordinates
Survey fees vary with site size, slope, vegetation, access and adjoining detail, so ask for a written scope and quote.
Should you get the survey before a pre-DA meeting?
Yes, where you can. A pre-lodgement meeting is most useful when officers can see real levels and neighbouring windows rather than a sketch over an aerial photo. City of Parramatta also says that, for certain development types, if no pre-lodgement meeting is held before lodgement, Council will not request amended plans or additional information. See our guide to preparing for a pre-DA meeting.
Frequently asked questions
Is a detail survey the same as a boundary survey?
No. A detail and level survey records features and levels; a boundary identification survey confirms where title boundaries are on the ground. Many DA surveys combine both, but ask for the boundary work explicitly, especially for works within 1 m of a boundary.
Can my building designer or architect measure the site instead?
Not for the site survey. City of Sydney, Inner West, Parramatta and Blacktown all ask for a survey prepared by a registered surveyor. Designers can measure existing interiors for floor plans.
Do I need levels on my neighbour’s property?
Usually, to the extent your council specifies. City of Sydney asks for adjoining structures within 3 m of the boundary, Blacktown for adjoining ridge and eave levels, and Parramatta’s stormwater checklist for levels extending into adjoining properties.
How old can my survey be?
It depends on the council. Inner West states “within the last 5 years”, Parramatta asks for a “recent” survey, and City of Sydney requires the accompanying title to be less than six months old.
Does a survey show underground pipes and cables?
Generally only visible features such as pits and inverts. Buried services information comes from BYDA and utility records; easements come from the title, deposited plan and 88B instrument.
Do I need a new survey for a section 4.55 modification?
Not automatically. If the original survey is still accurate and within your council’s stated period, it can often be reused. If the change reaches areas or levels it did not cover, extend or update it.
Why do councils want the survey in AHD rather than a local datum?
Height controls, kerb levels, stormwater and flood information all use a common datum, and the Surveying and Spatial Information Regulation 2024 requires survey heights to relate to AHD or another approved datum.
How giantA can help
Planning a DA or CDC in Greater Sydney? We can brief your surveyor against your council’s checklist and coordinate the survey with plans, shadow diagrams, the SEE and consultant reports. Start with our DA/CDC checklist, see our services and architectural services, or ask giantA via Help.
Preferred sources (verify current versions)
- NSW Department of Planning — Application requirements (approved form, March 2022)
- NSW Planning Portal — How to submit a development application to council
- NSW Department of Planning — Guide to Complying Development (August 2023)
- Surveying and Spatial Information Regulation 2024
- Surveying and Spatial Information Act 2002
- BOSSI — Find a Registered Surveyor
- City of Sydney — Survey plan specifications for planning applications
- Inner West Council — DA Lodgement Guide for Applicants
- City of Parramatta — Application requirements
- Blacktown City Council — Small scale residential DA
- Before You Dig Australia (BYDA)